Staff Reporter:
Prime Minister Tarique Rahman has directed the authorities concerned to engage independent price assessment companies to scrutinize the procurement costs of major development projects, strengthen manpower planning and promote sustainable construction materials.
State Minister for Planning Md. Zonayed Abdur Rahim Saki yesterday disclosed the directives while briefing journalists yesterday at the NEC conference room after the meeting of the Executive Committee of the National Economic Council (ECNEC) chaired by the Prime Minister at the Bangladesh Secretariat.
Saki said the Prime Minister approved a proposal to involve domestic or foreign price assessment companies in examining the costs of expensive equipment and specialized procurement items.
“Where the expenditure involves a substantial amount, we should appoint price assessment companies to verify the costs. This will introduce independent third-party scrutiny and establish an institutional system of checks and balances,” he said.
The state minister said the Planning Commission had already introduced measures to involve relevant specialists in examining equipment and procurement costs that do not fall under the approved rate schedule.
He said the government was also developing software that would use artificial intelligence (AI) to check whether project expenditure follows the approved rate schedule.
“Individual officials or project authorities may not always have the technical expertise to assess highly specialised equipment. We need an independent verification process so that project costs remain justified and excessive expenditure does not take place,” Saki said.
He said the Prime Minister specifically directed the authorities to apply the price assessment mechanism during the tender document preparation and procurement processes for the projects involving the construction of medical college hospitals and the expansion of the National Institute of Gastroenterology Hospital.
Manpower planning in health projects:
The Prime Minister also instructed the authorities to determine the required number of doctors, nurses, technicians and other skilled personnel at the initial stage of healthcare projects.
Saki said the government would no longer wait until projects approach completion to seek manpower approval, a practice that often delays the operation of newly constructed hospitals and leaves expensive equipment unused.
“Manpower approval must come alongside project implementation. The authorities must secure the necessary approval from the Ministry of Public Administration and the Ministry of Finance at the beginning and complete the required training before the project ends,” he said, quoting the Prime Minister’s direction.
He said the government would also incorporate training requirements into procurement conditions so that equipment suppliers could provide specialised training to medical personnel.
The state minister added that the government planned to increase investment in health education to develop doctors and technicians with the necessary specialised skills.
Review of GO-NGO collaboration:
Saki said the meeting also discussed delays in implementing projects under government-non-government organisation (GO-NGO) partnerships.
He cited a healthcare centre project in Char Fasson upazila of Bhola district, which faced repeated delays because the partner NGO could not provide its committed 20 percent share of the project cost, while the government was supposed to provide the remaining 80 percent.
The project received approval for its fourth revision, including a six-month extension.
He said the Planning Ministry had prepared proposals to revise the existing GO-NGO collaboration framework.
“We need to examine how government-NGO partnerships should operate and establish clearer guidelines. The Planning Ministry will discuss the proposals with the relevant ministries before placing the issue at the next National Economic Council meeting,” he said.
Gradual shift towards uniblock roads:
The Prime Minister also directed the authorities to gradually increase the use of uniblock materials in rural road construction under the Herringbone Bond (HB) road development program.
Saki said the government planned to reduce dependence on traditional brick roads because uniblock roads offer greater durability and can help reduce environmental damage caused by brick kilns.
Under the proposed approach, authorities will use 50 percent uniblocks and 50 percent bricks in the first year, 60 percent uniblocks and 40 percent bricks in the second year, and 70 percent uniblocks and 30 percent bricks in the third year if the program continues.
“Although uniblock roads may initially cost more, they offer greater durability and provide better convenience for people. We also want to reduce the environmental damage associated with the expansion of brick kilns,” he said.
The HB road program mainly covers rural roads that have not yet received official identification and therefore do not fall under the regular road maintenance responsibilities of the relevant agencies.
Saki said the government wanted to accelerate rural infrastructure development by revising ongoing projects and incorporating additional components rather than spending time preparing entirely new projects.