Metro Rail up to Kamalapur likely in Jul next yr

Staff Reporter:

The much-anticipated extension of Metro Rail’s MRT Line-6 from Motijheel to Kamalapur is expected to open for commercial operations in July next year.
“The overall physical progress of the civil construction work on the Motijheel-Kamalapur extension of MRT Line-6 has reached 84.85 percent,” Project Director of the Dhaka Mass Transit Development Pro-ject (MRT Line-6), Brigadier General (Retd) Md Abdul Wohab, told yesterday.
He said mechanical, electrical and plumbing (MEP) works at Kamalapur station are underway, while equipment manufactured abroad will be installed soon after being brought into the country.
According to project details, electro-mechanical works on the extension have progressed by 58 percent, while construction of the 1.16-kilometre viaduct on the Motijheel-Kamalapur extension has been com-pleted, and it has been handed over to Contract Package-7 (CP-07) for rail track installation.
The structural work on Kamalapur MRT Station has also been completed, while MEP and architectural works are underway and are expected to be finished by December 31, 2026.
Meanwhile, work on seven integrated electro-mechanical subsystems under CP-07 is progressing. These include electrical and track systems, signaling, automatic fare collection (AFC), platform screen doors (PSD), telecommunications, lifts and escalators.
The 21.26-kilometre MRT Line-6, extending from Uttara North to Kamalapur, is progressing towards completion. As of September 30, 2026, the physical progress of the Uttara North-Motijheel section stood at 99.67 percent, while civil construction work on the Motijheel-Kamalapur extension had reached 84.85 percent.
Once the final section becomes operational, MRT Line-6 will connect Uttara North (Diabari) directly to Kamalapur Railway Station, completing the full 21.26-kilometre route.
The line will have 17 stations, including major stops at Mirpur-10, Agargaon, Farmgate and Dhaka Uni-versity.
The metro rail began operating on the Uttara–Agargaon section on December 28, 2022. The Agargaon–Motijheel section opened on November 4, 2023. Since the Motijheel section opened, the metro rail has become a vital transport link for Dhaka residents, serving thousands of commuters daily.
Under the current schedule, the first trains depart from Motijheel at 7:00 am and Uttara North at 6:40 am.
On an average more than 4.0 lakh passengers are traveling on the metro rail since its launch, while on September 10 over 5.0 lakh passengers travelled on the metro, according to project information.
Revenue from ticket sales is also increasing as passenger numbers grow.

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Advertisement

You May Also Like

FRONTPAGE

Staff Reporter: Prime Minister Tarique Rahman yesterday said the government is pursuing clear policies and action plans to ensure education, safety, dignity and a...

BACK PAGE

Staff Reporter: Prime Minister Tarique Rahman yesterday said his government is committed to ensure the rights and security of every citizen of the country...

FRONTPAGE

Staff Reporter: Prime Minister Tarique Rahman yesterday sought Canadian cooperation in education, health, energy and agriculture, alongside food security, technical education and climate financing,...

FRONTPAGE

Staff Reporter: Bangladesh and the European Union (EU) have discussed strengthening cooperation to curb illegal mi-gration and human trafficking with a view to expanding...

Copyright © 2023 The Good Morning. All Rights Reserved.
Editor and Publisher: Enayet Hossain Khan
70, Pioneer Road, Kakrail, Dhaka- 1000, Bangladesh.
Phone: +88-01711424112, +88-01847255828
Email: dailygoodmorning@yahoo.com, thegoodmorningbd@gmail.com
Designed & Maintained By TECHIENET SOFTWARE ltd.