RNPP resumes power supply to national grid

A Correspondent:

Pabna: The first unit of the Rooppur Nuclear Power Plant yesterday resumed experimental electricity supply to the national grid for the second phase, beginning transmission at 10:20 am.
Project Director of the Rooppur Nuclear Power Plant Construction Project Dr Md Kabir Hossain said the unit would supply around 300 to 350 megawatts of electricity to the national grid for 10 to 24 hours during this phase.
Various technical tests will be conducted during the period to assess the performance of the plant’s power generation system and its integrated operation with the national grid, he said.
Earlier, on November 17, the plant began its first-ever experimental electricity supply to the national grid following extensive testing and necessary technical preparations.
During the first phase, the plant’s first unit generated up to 375 megawatts of electricity and supplied it to the grid for around eight and a half hours. The estimated market value of the electricity supplied during that period was around Tk 2 crore. The grid connection was subsequently disconnected at 11:50 pm.
Managing Director of Nuclear Power Plant Company Bangladesh Limited (NPCBL) Dr Md Zahedul Hasan said that the First Grid Connection (FGC) involved close monitoring of the performance and stability of the turbine, generator and integrated operational system with the national grid.
Following satisfactory test results and a necessary interval, the unit was reconnected to the grid for the second phase, he said.
He added that the connection would again be disconnected after several hours of monitoring, depending on the overall situation.
Zahedul Hasan said the electricity supply had been made possible within the shortest possible time through the dedicated efforts of NPCBL engineers, scientists and officials, taking into account the country’s power demand and shortage.
During the subsequent testing phases, power generation will be increased or reduced as required. The unit may also be temporarily shut down to conduct specific tests, he said.
Power Grid Bangladesh PLC (PGB) will take necessary measures to maintain the balance of the national grid in response to fluctuations in electricity generation.
Appreciating the efforts of NPCBL officials and employees, the managing director said all-out efforts were underway to bring the first unit to full-capacity power generation and supply before the next summer, between February and March 2027.
He expressed hope that the unit would then be able to supply around 1,150 megawatts of electricity to the national grid, significantly easing the country’s power shortage during the summer.
Project officials said grid connection was a crucial technical step in ensuring coordination between a power plant’s generation system and the national transmission network.
They said generation capacity would be increased gradually in line with the guidelines of the International Atomic Energy Agency (IAEA) and international safety standards.
After completing the necessary tests and obtaining the required licences and regulatory approvals, the first unit’s generation capacity is expected to be gradually raised to 100 percent.
The Rooppur Nuclear Power Plant is being built with two units, each having a generation capacity of 1,200 megawatts. Once both units become operational, the plant will have a combined capacity of 2,400 megawatts.

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Advertisement

You May Also Like

FRONTPAGE

Staff Reporter: A four-member delegation of the National Citizen Party (NCP), led by its Convener Nahid Islam, yesterday met Prime Minister Tarique Rahman at...

FRONTPAGE

Staff Reporter: Prime Minister Tarique Rahman yesterday said his government is working sincerely to simplify and speed up foreign investment as South Korea’s SK...

AROUND THE COUNTRY

A Correspondent: Gazipur: A woman, her six-year-old son, and a young man suffered severe burn injuries in a fire triggered by a gas cylinder...

AROUND THE COUNTRY

A Correspondent: Sylhet: A youth was stabbed to death allegedly by his cousin over a dispute regarding rainwater falling from a tin roof onto...

Copyright © 2023 The Good Morning. All Rights Reserved.
Editor and Publisher: Enayet Hossain Khan
70, Pioneer Road, Kakrail, Dhaka- 1000, Bangladesh.
Phone: +88-01711424112, +88-01847255828
Email: dailygoodmorning@yahoo.com, thegoodmorningbd@gmail.com
Designed & Maintained By TECHIENET SOFTWARE ltd.